Environment & climate Maharashtra
The Maharashtra Forest Department has ordered an immediate halt to construction of Adani Green Energy's 1,500 MW Tarali Pumped Storage Project in Satara district, because of the lack of mandatory…
Wednesday, 18 November 2026 · 7:53 pm IST
The move comes amid controversy after the company reduced the project's estimated cost by 99% which would sharply cut the company's proposed wildlife conservation contribution.
At a meeting with Forest Minister Ganesh Naik, the company clarified that RS 5,675 crore was the total project cost, while Rs 56.75 crore covered only preliminary studies and feasibility work.
The revised estimate would reduce the required conservation contribution from Rs 227 crore to Rs 2.27 crore.
Sources PTI